President Director of PT PLN Nur Pamudji Resigns

President Director of PT PLN Nur Pamudji Resigns


President Director of PT PLN ( Persero ) Nur Pamudji offered to resign as a manifestation of his disappointment with the Attorney General's investigation of the turbine procurement project .

Procurement Turbine Power Plant project Gas and Steam Belawan , Medan , North Sumatra , fiscal year 2007-2009 and routine maintenance in 2012 , he could not protect employees who work both from the professional and legal issues .

The case began when some of the gas turbine power plant and steam ( PLTGU ) Belawan has operated for 120,000 hours , some time ago . In fact , according to the standard operation , when the engine is already operating 100,000 hours , the engine generator should be used for maintenance rested .

The delay was due to the condition of the turbine maintenance supplies in North Sumatra mediocre, so if the plant ceases to operate will result in power outages .
For the PT PLN then held auction workmanship turbine engine life extension with its own price estimate ( HPS ) established the company . Determination of HPS was based on price surveys , several other standards , and there is a reference price of goods . But when the machine is checked , it turns out necessary additional work because there are components that must be replaced so that the construction cost exceeds HPS .
Attorney General's investigation stated , the difference in value Belawan project consisting of the value of the main contract and contract changes due to the extra processing it as bubbles HPS funds and are considered detrimental to the country . Attorney General's investigation also assessed the ability of the machine is not in the contract because it only operates 123 megawatts ( MW ) .

Though the contract mentioned capacity of 140 MW .
Actually, the installed capacity of turbines at the 140 MW Combined Cycle Power Plant Belawan . However, due to the load during the daytime low power , the engine is operating under capacity.
" The operation was appropriate electrical power what the customer requested . When daylight low load , the engine is not operating at full capacity , and it is considered not appropriate contract , " said Senior Manager Corporate Communications PT PLN Bambang Dwiyanto . | ASN-013/MJF